Cooling capacity, where occupants benefit from additional cooling capacity
In this example, a building is served by a single system of more than 250kW capacity under single control with an additional air conditioning system rated at 100kW.
An air conditioning inspection on a system with a cooling capacity greater than 250kW should have been carried out by 4 January 2009. A revised air conditioning inspection report would be required every 5 years from the date of the initial inspection.
Mike Gordon
Comments