Control of equipment

The building owner or manager is responsible for ensuring there is an air conditioning inspection report for the central system and the building occupier is responsible for ensuring there is an air conditioning inspection report for the equipment they have installed. In this example each party controls less than 250kW and the first inspection must have happened by 4 January 2011.

The central air conditioning system for the building is 150kW.

Tenant 1 occupies floors 1 and 2 and had additionally installed their own system of 110kW.

The landlord is the relevant person for the control of the central (150kW) system. The tenant is the relevant person for the control of the additional system (110kW) on floors 1 and 2.